Construction Update: August 19, 2022
Work completed the week of August 15:
This week, Broadway Street to 320 6th Street West was reclaimed and is now a gravel surface. Comcast crews installed new communication utilities on the north side of 6th Street West and temporary water service lines are in the process of being installed.
Work planned the week of August 22:
Work will include:
- Homeowners should be on temporary water near mid to end of next week. Residents receiving temporary water service will receive fliers next week with more specifics on this process.
- Comcast crews plan to continue work onsite relocating communication lines underground on the north side of 6th Street West.