Construction Update: August 12, 2022
Work completed the week of August 8:
This week, the final retaining wall was removed and replaced with the new large block style. Additional project erosion control devices were installed.
Work planned the week of August 15:
Work will include:
- Setup of temporary watermain piping for homes on the east end of 6th Street is anticipated to take place on Tuesday and Wednesday (August 16 and 17). Homeowners should be on temporary water near the end of next week. Residents receiving temporary water service will receive a notice with more specifics on this process.
- 6th Street from Broadway Street to 320 6th Street West will be reclaimed beginning Monday. The roadway will be a gravel surface after the reclamation process.