Construction Update: August 5, 2022
Work completed the week of August 1:
This week, several of the existing small-block retaining walls were replaced with new large-block walls.
Work planned the week of August 8:
Setup of temporary watermain piping for homes on the east end of 6th Street will begin Thursday and Friday (August 11 and 12). Homeowners are anticipated to be on temporary water beginning the week of August 15. Residents receiving temporary water service will receive fliers next week with more specifics on this process.