Construction Update: September 23, 2022
Work completed the week of September 19:
This week, nearly half of the new watermain proposed in the project was installed and additional ditch finish grading improvements were completed along the corridor. Storm sewer utilities installation continued, and the removal of the existing asphalt trail began. In addition, the street reclamation from Lylewood Parkway to the west end of the project (community park) has been completed.


Work planned the week of September 26:
Work will include:
- Additional watermain installation will continue near the 6th Street/Broadway Street Intersection.
- Installation of new water services will start.
- Testing of newly installed watermains and services will take place.