Posted on: November 25, 2022
Construction Update: November 25, 2022
6th Street West is now open to all traffic after several months of closure for major improvements to the corridor. Since September, water services, storm sewers, street and trail lighting preparation, and various util...
Read on...
Construction Updates - 6th Street West
Posted on: November 18, 2022
Construction Update: November 18, 2022
6th Street Scheduled to Reopen Wednesday, Nov. 23 at Noon
Crews have been working hard to prepare for the reopening of the corridor next week. The installation of the first lift of street and trail pavement is now comp...
Read on...
Construction Updates - 6th Street West
Posted on: October 27, 2022
Construction Update: November 11, 2022
Work completed the week of November 7:
Much of what took place this week was a continuation of work from last week, such as the installation of electrical lines for walkway and street lighting. Additionally, 6th Street...
Read on...
Construction Updates - 6th Street West
Posted on: October 27, 2022
Construction Update: November 4, 2022
Work completed the week of October 31:
This week, crews finished preparing 6th Street for concrete curbing installation, planned for next Monday or Tuesday. Xcel Energy completed the transfer of new power services to pr...
Read on...
Construction Updates - 6th Street West
Posted on: October 27, 2022
Construction Update: October 28, 2022
Work completed the week of October 24:The installation of all underground city utilities was completed this week, in addition to Xcel Energy installing new utilities. The electrical sub-contractor continued installing ...Read on...
Construction Updates - 6th Street West
Posted on: October 27, 2022
Work completed the week of October 17:
This week, crews installed a new 15” draintile on the north side of the curbline toward the east end of 6th Street. Xcel Energy continued installing new utilities, while the electrical sub-contractor installed new ele...
Read on...
Construction Updates - 6th Street West
Posted on: October 27, 2022
Construction Update: October 14, 2022
Work completed the week of October 10:
This week, construction on the watermain progressed and is nearly complete. 6th Street east of Community Park is prepared and paving began Friday, Oct. 14. The restoration of parti...
Read on...
Construction Updates - 6th Street West
Posted on: October 27, 2022
Construction Update: October 7, 2022
Work completed the week of October 3:
Over the last week, watermain construction continued with the installation of new water services. The placement of new storm sewer utilities continued, and the restoration of partial...
Read on...
Construction Updates - 6th Street West
Posted on: October 27, 2022
Construction Update: September 30, 2022
Work completed the week of September 26:
This week, watermain construction continued and portions of the new watermain were filled to start testing procedures. The new retaining walls along the corridor were painted. ...
Read on...
Construction Updates - 6th Street West
Posted on: October 27, 2022
Construction Update: September 23, 2022
Work completed the week of September 19:
This week, nearly half of the new watermain proposed in the project was installed and additional ditch finish grading improvements were completed along the corridor. Storm sewe...
Read on...
Construction Updates - 6th Street West
Posted on: October 27, 2022
Construction Update: September 16, 2022
Work completed the week of September 12:
This week, the storm sewer utility construction continued throughout the corridor and watermain reconstruction has commenced.
Work planned the week of September 19:
Work will inc...
Read on...
Construction Updates - 6th Street West
Posted on: October 27, 2022
Construction Update: September 9, 2022
Work completed the week of September 5:
This week, the storm sewer utility construction continued throughout the corridor. Comcast crews were onsite to commission the recently installed utilities. Finally, grading impr...
Read on...
Construction Updates - 6th Street West
Posted on: October 27, 2022
Construction Update: September 2, 2022
Work completed the week of August 29:
This week, new storm sewer utility construction began throughout the corridor. Additionally, Comcast crews finished the installation of relocated communications utility lines.
&...
Read on...
Construction Updates - 6th Street West
Posted on: October 27, 2022
Construction Update: August 26, 2022
Work completed the week of August 22:
This week, the installation and testing of the temporary watermain took place on the corridor. Additionally, Comcast crews were onsite to continue the relocation of underground commu...
Read on...
Construction Updates - 6th Street West
Posted on: October 27, 2022
Construction Update: August 19, 2022
Work completed the week of August 15:
This week, Broadway Street to 320 6th Street West was reclaimed and is now a gravel surface. Comcast crews installed new communication utilities on the north side of 6th Street West ...
Read on...
Construction Updates - 6th Street West
Posted on: October 27, 2022
Construction Update: August 12, 2022
Work completed the week of August 8:
This week, the final retaining wall was removed and replaced with the new large block style. Additional project erosion control devices were installed.
Work planned the week of August ...
Read on...
Construction Updates - 6th Street West
Posted on: October 27, 2022
Construction Update: August 5, 2022
Work completed the week of August 1:
This week, several of the existing small-block retaining walls were replaced with new large-block walls.
Work planned the week of August 8:
Setup of temporary watermain piping for homes ...
Read on...
Construction Updates - 6th Street West
Posted on: October 27, 2022
Construction Update: July 29, 2022
Work completed the week of July 25:
During the first week of construction, tree removal throughout the project area was completed and erosion control devices were installed.
Work planned the week of August 1:
During the week...
Read on...
Construction Updates - 6th Street West
Posted on: October 27, 2022
Construction Update: July 25, 2022
6th Street West closure begins July 25
Roadway construction begins July 25 along 6th Street West between Jonathan Carver Parkway and Broadway Street. 6th Street is closed to all through traffic between Lylewood Parkway and...
Read on...